Microsoft Project

Frequently Asked Questions

Student contributions welcome.

Table of Contents

  1. How do I get a chart of costs accrued during a project?

How do I get a chart of costs accrued during a project?

First select View/Resource Graph.

Then you may need to do some or all of the following.

Use Project/Filtered for ... to select All resources
Use Format/Details...to select Cost
Use Format/Bar styles ...to do the following
Under Filtered resources/Show as ...you have, say, Bar
Under everything else, you have Don't show
Back to Top