  1. RECORDS


    1. The Electrical Contractor shall submit to the UIC Telecommunications Engineering & Design a complete set of as-built drawings. These drawings shall show every detail of the construction upon completion of the project.


    2. Cable records shall be submitted to UIC Telecommunications Engineering & Design and shall include complete and accurate documentation showing every splice and cross-connection by cable number and pair, as well as the information outlet numbers and location. The records must conform to the cable numbering system established by the UIC Telecommunications Department. A copy of these records shall also be supplied to the UIC Commit operators and the Installation Section.


    3. With the supervision of UIC Telecommunications Engineering & Design representative, the contractor shall test every pair in every cable installed end-to-end after splicing and terminating is completed. Maximum allowable defective pairs will be limited to one percent of the total number of pairs in any cable, and a maximum of two pairs in a twenty five pair binder group.


    4. The contractor shall prepare and submit to UIC Telecommunications Engineering & Design cable distribution "as-built" drawings which reflect the following:


      1. Exact route of all outside plant cabling from the NODE to the IDF, including underground conduits and tunnel routes. Included shall be a detailed cross-section drawing of all conduits encased in concrete with all dimensions, reinforcements, and sill.


      2. Cable size, count, gauge, and length of all cables installed.


      3. Every splice by cable number and pair count.


      4. The cable numbering system shall conform to the existing University numbering system.


    5. 20.5 Contractor shall prepare and submit "as-built" floor plan drawings which reflect:


      1. Building entry, IDF, FDF, cable tray, raceway, and information outlet locations.


      2. Corrected risers, conduit sizes, splice locations, cable counts, terminals, and patch panels.


    6. Label each drawing "AS-BUILT" in neat, large printed letters. Markings must be legible and with permanent ink. Water based ink shall not be used due to easy smearing. These drawings will also be submitted in Auto-CAD 12 (or later) on 3.5" disks.


    7. The Communications Contractor shall provide the University with field corrected floor plan drawings prior to acceptance of the work by the University.


    8. The Communications Contractor shall provide the University with all testing documentation prior to the University acceptance of the work.


    9. Hard copy of all test results shall be submitted in three ring binders, unless the tests themselves are provided on 3.5" disks ( see Testing ).